Barn Building Update 2


The Foundation

Work continues on the barn, the start of which is documented in this post.

They had originally been using standard hand-held compactors to compact all the dirt and gravel being laid out as the base, but at a certain point that wasn’t enough and they upgraded to this monster of a roller.

They also started putting in some of the drain tile that will go around the edge of the barn to direct water away from the building. That is that little pile of dirt that seems to be just hanging out in the middle. Still need to work out an overall waterflow and containment strategy for our whole property but drain tile around the barn is a good first step.

After everything was rolled and compacted the equipment people came and picked up the big roller and replaced it with another large machine which they’ve so far been using to unload and move the various materials that have been steadily arriving. From the looks of it I think it will also be the machine that gets the trusses up in the air. They spent the rest of the day measuring and remeasuring and then remeasuring and then just one more time lets remeasure the dimensions of the barn (happy they are being so thorough!) and then made my math heart just sing by using the Pythagorean theorem to square the corners! 

The day after that they went around and measured out the location for every support beam and truss and then two of the crew used an auger attachment to dig holes for each location while the other two painted the bottoms of the posts with white rubber roof coating.

Apparently the first round of holes weren’t deep enough because they dug them even deeper the next day. Not sure if I should be concerned that the holes farthest away from the house have water in them. They also re-marked out the locations of everything and smoothed down the tops of most of the dirt piles.

Then they laid out these short cement discs at each hole location as well as the posts that will go in each hole. I have no idea how they got the cement discs in each hole in such a way that it is sitting level and in the correct location but I’m trusting that they know what they are doing. 

Nate and I spend a lot of time wondering how the heck something is going to work or in some cases what they are doing or why they are doing it. Luckily we have some help supervising the work.

1 thought on “Barn Building Update 2

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes:

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>